Civil construction work on the Central Puget Sound Regional Transit Authority’s (Sound Transit) Lynnwood Link extension project in the US has reached the halfway completion mark.

All 188 columns of the project are now complete, with the light rail service slated to commence operations in 2024.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

Rail work has started on several sites, while the construction of all ten bridges has reached 80% completion.

So far, 530 of 533 girders have been set, with the rest expected to be placed before the end of this year.

Construction work is also advancing on three new garages, which will support the extension.

Garages at the Shoreline North/185th and Shoreline South/148th stations will each contain around 500 parking lots.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The new garage at Lynnwood Transit Centre, set in a five-story building, will feature 1,670 parking stalls, with plans to open in the spring of 2023.

Civil construction on the extension is being implemented by Stacy and Witbeck/Kiewit/Hoffman JV and Skanska Constructors L300 JV.

The $3.1bn project has procured up to $1.17bn from the Federal Transit Administration under a Full Funding Grant Agreement.

Sound Transit said in a statement: “In addition, the US Department of Transportation’s Build America Bureau executed a $658m low-interest loan supporting the project, including new LRVs and support facilities. At its initial signing in 2016, this loan saved regional taxpayers an estimated $200m to $300m through lower interest costs.”

Lynnwood Link, along with other extensions presently undergoing construction, will increase the length of the region’s light rail system by more than twofold.

Lynnwood Link light rail service will operate between south Snohomish County, the University of Washington, downtown Seattle, the Eastside, Sea-Tac Airport, and Federal Way.

It will feature four new stations at Lynnwood, Shoreline, Mountlake Terrace, and Seattle.

Earlier this month, Sound Transit began early scoping work on the Everett Link regional light rail extension.

Railway Technology Excellence Awards - Nominations Closed

Nominations are now closed for the Railway Technology Excellence Awards. A big thanks to all the organisations that entered – your response has been outstanding, showcasing exceptional innovation, leadership, and impact across the defence sector.

Excellence in Action
MTR Corporation and Dragages Hong Kong triumphed in three categories – Research & Development, Environmental and Safety – for their Kwu Tung Station project . Learn how this future Northern Link–East Rail Line interchange sets new benchmarks in digital construction, decarbonisation and safety management.

Discover the Impact