The Government of Queensland in Australia has announced that Bundaberg station improvement and other associated project works have begun to improve the Wide Bay rail network.

According to Queensland Minister for Transport and Main Roads Mark Bailey, the work programme includes a A$21.8m ($16.2m) signalling upgrade project in Bundaberg, as well as another A$12m ($8.9m) investment to rehabilitate the Burnett River rail bridge.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

Bailey said: “With three long distance trains servicing the station – the Spirit of Queensland, Spirit of the Outback, and Tilt Train – and more than 91,000 visitors in 2017, there is no doubt that Bundaberg station is Queensland’s most popular regional train station.

“We’ll be looking to continue this momentum by making progress on a number of our key investments in the Bundaberg and Wide Bay regions.”

“We’ll be looking to continue this momentum by making progress on a number of our key investments in the Bundaberg and Wide Bay regions throughout 2018 and 2019.”

He added that the existing signalling systems at Bundaberg and Bundaberg North will be replaced with a new system.

A new power equipment room equipped with a new generator machine will also be installed near Bundaberg station to ensure power is supplied during unplanned power disruptions or severe storms.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Rail signalling upgrade works between the Kolan/Mt Perry and Thabeban Road level crossings have already started, while works at the Walker Street level crossing are due to start in September this year.

Bailey stated: “The final leg of the project will commence next year, with upgrades to the rail signalling at Hanbury Street level crossing and the installation of a new pedestrian crossing at Perry Street, which Queensland Rail is currently working with local council to finalise.”

The Burnett River rail bridge upgrade works have also commenced, where the workers have completed the sandblasting.

The bridge serves as a key piece of infrastructure on the North Coast railway line.

The Bundaberg re-signalling project is expected to be completed in August next year and the Burnett River bridge upgrade is due to be commissioned in the middle of this year.

Railway Technology Excellence Awards - Nominations Closed

Nominations are now closed for the Railway Technology Excellence Awards. A big thanks to all the organisations that entered – your response has been outstanding, showcasing exceptional innovation, leadership, and impact across the defence sector.

Excellence in Action
Omnevo’s digital Order-to-Seat platform has won the Innovation Award for Onboard Retail, redefining how passengers order, pay, and receive F&B at their seats. Learn how this solution is cutting waste, streamlining logistics, and enabling operators to personalize and modernize onboard retail.

Discover the Impact