It is approaching almost 60 years since the final section of Norway’s Nordland Line was completed. Running 729km from Trondheim, situated in the centre of the country, to Bodø in the north, it carries the distinction of being one of the very few rail lines on earth to pass through the Arctic Circle.

When it was officially opened in 1962, it also represented one of Norway’s largest, post-war infrastructural investments. But, for all its splendour, the Nordland Line – together with the rest of Norway’s rail network – is now showing its age, with signalling failures increasingly commonplace.

This has forced Bane NOR – the state-owned group that has been charge of Norway’s national railway infrastructure since 2017 – into action. In late October, it announced a new €3bn programme that will see the entire network re-signalled over the next decade.

As part of the ambitious project, all 336 existing signal boxes on the 4,200km network will be replaced with a single data centre. This centre, in turn, will house a set of electronic interlockings able to communicate with field equipment thanks to a 5,000km optic network.

A major contract, worth €800m, has been awarded to Siemens Mobility, which will provide new interlockings and European Train Control System (ETCS) lineside technology. Elsewhere, both Alstom and Thales have won bids to supply onboard equipment and a traffic management system, respectively.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Bane NOR has also opened a new a European Rail Traffic Management System (ERTMS) training and signalling simulation centre at an existing railway facility just outside Oslo. As well as training up to 5,000 rail workers, the lab will serve as a test laboratory for the integration of lineside and onboard hardware and software.

The pledge marks Norway out as the first country to commit itself to operating with a single digital interlocking. The ERTMS project also serves as a clear indication of the increasing role digitalisation will play on the network in decades to come.

Below, Sverre Kjenne, Bane NOR’s head of digitisation and technology, explains how the project came about and the advantages it is expected to bring to bear.

Ross Davies: Why the decision to re-signal the entire Norwegian rail network now?

Sverre Kjenne: The trigger for all of this is that we have 336 interlockings in Norway, with 80% of them based on relay technology last bought a few years ago. There was an urgent need for renewal.

RD: Have infrastructure failures on the line also contributed to the decision?

SK: Yes, that is correct. If you look at Norway – out of all the delays on Norwegian rail, around 60% come out of the infrastructure. And out of that 60%, close to 50% comes from the signalling area.

So, in addition to the urgent need for renewal, there was also a need for better punctuality.

RD: When did Bane NOR first conceive of the new ERTMS test and training centre? What kind of work will be taking place there?

SK: We realised a few years ago that we needed to have a centre where we could educate quite a number of people. We estimated between 5,000- 8,000 people in total will need to somehow be trained on ERTMS. We’re talking about train drivers, maintenance people and others.

In addition to that, we also want to have a centre where the suppliers could cooperate, where the different equipment could be tested. We had a look around at different facilities and came up with the centre where we also have the opportunity to rebuild trains.

RD: What benefits will the re-signalling programme bring in terms of capacity on Norway’s railways?

SK: Short term, the number one benefit will be that we can do the renewal while maintaining operations on Norwegian rail. That has been a trigger. Secondly, it will add safety by having continuous supervision of both the speed and position. Thirdly, you increase punctuality by having less signalling errors.

The capacity increase will probably come when we get to ATO [automatic train operations].

RD: So, capacity increase is more of a long-term objective? Some reports I’ve seen claim the programme could create an uptick of up to 30% – is that the case?

SK: Yes, it is a long-term goal; ERTMS will be a building block for the future. And the future will give us an opportunity for capacity increases.  

I have also seen that figure of 30% increase you mention used by several vendors. However, at this point in time, we want to be careful with estimates on future capacity increase. The answer is probably that it all depends. Norway has a lot of single-track lines.

RD: What challenges do you expect to encounter along the way?

SK: One traditional challenge is getting the trains delivered on time, as we don’t own the rolling stock. This means we need to work together with the train owners. And the way that we have done this is that the Norwegian Government is providing 50% of the funding for the rebuild of the trains, provided the vehicle owners make the trains available on time and on schedule. So, we’ve had some financial incentives on that side.

RD: You’ve awarded three main contracts to Siemens, Alstom and Thales – was that quite a straightforward tender process?

SK: In some ways, it was a straightforward tender process. That said, it was challenging in terms of all the different requirements put forward and ensuring that we ended up with the best possible solutions, to be delivered on time. It was the culmination of close financial evaluation.

RD: With digitalisation now here to stay, how excited are you about the arrival of ATO further down the line? 

SK: We have a few bottlenecks where an ATO solution obviously should have huge benefits. I do believe ATO, in general, will be made available. There’s a good argument for it. Because, capacity-wise, ATO will deal with these bottlenecks. It will also reduce power consumption significantly.