Manchester Metrolink, United Kingdom




Key Data


Manchester Metrolink is England's first modern street-operating light rail system. It includes three lines that serve the towns of Bury, Altrincham and Eccles and meet at Manchester City Centre. Metrolink incorporates the features of heavy rail and trams.

Becoming the UK's second operational public tramway (after Blackpool) when it opened in stages during 1992, Manchester Metrolink was the country's pioneering modern-era system. In spite of success in attracting passengers and estimated to have reduced car usage by five million journeys a year, Metrolink's clear potential became severely limited by a lack of investment.

Totalling 37km (23 miles), current routes are: Altrincham-Manchester City Centre-Bury; Altrincham-Manchester Piccadilly station; Bury-Manchester Piccadilly and Eccles-Manchester Piccadilly.

The project

Metrolink is owned by Greater Manchester Passenger Transport Executive (GMPTE), which offers passengers in its area covering ten metropolitan authorities a range of tickets also covering heavy rail and buses. It is operated by Stagecoach Group under a contract.

"In May 2008 the government gave final approval for the Phase 3a expansion, a £600m project to almost double Metrolink's length."

From initial planning in the 1980s and construction beginning in 1990, the initial 31.5km (20 mile) Phase 1 operation was the product of the Greater Manchester Metrolink (GMML). The contract was worth £145m. GMML is a consortium of GEC Alsthom Transportation Projects, John Mowlem, Amec and GMPTE.

The consortium GMA Group, consisting of GEC Mowlem, AMEC and GM Buses, was involved in Manchester City Centre's Service diversions programme. GMA was succeeded by Altram (Manchester) between 1997 and 2007.

Operator Serco was replaced in April 2007 by Stagecoach with a ten-year contract, already responsible for Sheffield Supertram. Phase 2, the Eccles line project costing £160m, was completed by 2000, thereafter stimulating rejuvenation of the former Manchester Ship Canal area in Salford.

In May 2008 the government gave final approval for the Phase 3a expansion, a £600m project to almost double Metrolink's length. The longest section will be the conversion of the heavy rail 'Oldham Loop' and Rochdale route, leaving the Bury line near Metrolink's Queens Road operations and maintenance centre. East from Piccadilly, a new eight-stop line will go to Droylsden.

The extension also includes lines to Chorlton in South Manchester and a small spur to MediaCityUK from Harbour City. Extension of the line to East Didsbury, Manchester Airport, Ashton-under-Lyne, and the town centres of Oldham and Rochdale was approved in May 2009.

The shortest of the new lines will leave the Altrincham line near Trafford Bar for a terminus at St Werburgh's Road in Chorlton-cum-Hardy. The project is part-funded by loans that are due to be repaid over 30 years.

Expansion work being carried out by GMPTE includes the construction of 20 miles of new track and 27 new stops. The tram fleet will also be expanded by 40 new trams to 72.

The trams to mediacity:uk are scheduled to start their operations in summer 2010 while services to Chorlton and Central Park will begin in spring 2011 and to Oldham Mumps in 2011. The lines to Rochdale and Droylsde are scheduled to be opened to traffic in 2012.

In May 2008, the UK Government granted £244m for extensions to Oldham, Rochdale and Chorlton. As of March 2010, the three extensions are under construction. The government also granted £120.9m to two tram extensions to Ashton and East Didsbury .

The extension to East Didsbury includes the construction of five halts and is expected to be completed by summer 2013, while the extension to Ashton includes the construction of new track and four halts. The Ashton extension is scheduled to be completed by winter 2013/14.

Infrastructure

The first phase, Bury in the north to Altrincham in the south-west via Manchester city centre, mostly uses former heavy rail alignments. Creating Metrolink solved a problem shared by two free-standing railways (Manchester Victoria-Bury and Manchester Oxford Road-Altrincham) each a vital transport link but with life-expired non-standard (but different) electrification.

A comparatively short section of on-street grooved track in the city centre linked the lines via a city focal point at Piccadilly Gardens, with a new connection also created between the main rail termini, Piccadilly and Victoria. The new system adopted the tramway standard of 750V dc overhead supply.

"Built at street level but beneath the high-level main line platforms, Piccadilly is the only entirely covered stop on the system."

Prior to access improvements, stations on the former railways were used with little modification beyond restricting the usable platform section to match tram lengths.

To be compatible with the railway-derived stops, 900mm-high platforms were built for the street stops, using ramps or lifts for level boarding of the high-floor tram fleet.

In addition to railway infrastructure, Metrolink features street running and some reserved stretches. A city centre stop south from Victoria for Manchester's Shudehill transport interchange was added in 2003.

Built at street level but beneath the high-level main line platforms, Piccadilly is the only entirely covered stop on the system. Currently a terminus, it is the also only one where all trams normally arrive and depart from different platforms.

A £102m emergency track improvement programme necessitated partial temporary closures from May 2007, with 20 miles of noisy and rough-riding rails replaced. Funded by GMPTE and the Department for Transport and with Carillion as main contractor, the programme also included new ticket machines and upgrading of stops.

Rolling stock

Components of the original 26 T-68 articulated two-car sets came from several suppliers, being assembled at Queen's Road. Articulated bodies and bogies were assembled at Firema in Milan, under contract to GEC Alsthom. Alstom built the wheels and axles in Salzgitter, Germany. Other components were British-made, including electric motors (Alstom, Preston) and pantographs (Brecknell Willis, Somerset). Maximum speeds are 80km/h (50mph) on rail alignments and 48km/h (30mph) on street sections.

In 1999, the fleet was bolstered by six (T-68a) for the Eccles extension, indicated by their 2000-series numbers, dot matrix destination displays, also retractable couplers and covered bogies, necessary for on-street running close to motor traffic. Three of the earlier fleet were similarly equipped.

In 2008 Stagecoach announced an 18-month refurbishment programme for the fleet of 32, giving at least another ten years of service. This will allow all fleet members work the Eccles line, as well as braking system and traction modifications to improve reliability. Internally the vehicles will be reworked with improved lighting and security cameras, plus changes for disability legislation compliance.

"In 2008 Stagecoach announced an 18-month refurbishment programme for the fleet of 32, giving at least another ten years of service."

Driven by a pressing need to increase Bury-Altrincham peak capacity, the next generation of Manchester trams was signalled by a £17m order for eight Bombardier/ Vossloh Kiepe trams from the Flexity Swift family. Similar to Cologne's high-floor K5000 series, they will be built at Bautzen and Vienna.

With four more ordered in November 2007 in connection with the mediacity:uk extension, the 200-capacity vehicles are due for delivery in 2009–2010.

Following the go-ahead for the Phase 3a expansion, in June 2008 GMPTE announced an order for 40 more trams that are being constructed by Bombardier in partnership with Vossloh Kiepe. Each tram will cost over £2m.

Signalling / communications

The system is overseen from the Queens Road control room. The Timperley – Navigation Road – Altrincham section is under Network Rail control, but operating procedures are the same as elsewhere. Previously poor in relation to modern international standards, communication with passengers using Metrolink is to improve under a programme including CCTV coverage, real-time indicators and on-board information.

All former heavy rail alignments, also the portion of the new route from just beyond G-Mex to the intersection with the existing Metrolink route to Altrincham, at Cornbrook, are controlled by absolute block signalling, mainly controlled by two-aspect colour light signals. To reduce problems of reliability and delay relating to the installed signalling system, GMPTE is investigating increasing the proportion of the network using 'line of sight' control.

The future

Extra stations (Buckley Wells, Abraham Moss and Chester Road) have been considered to give better passenger access on the former railway sections. Even with likely on-site extension, the Queen's Road depot could not handle the system's expansion and new facilities will be built near Trafford Park.

The next package of projected Metrolink expansions is Phase 3b; its funding was finally approved, with a small rise in council taxes, in May 2009. It will extend the system into Oldham and Rochdale town centres from the Phase 3a line, from Droylsden to Ashton-under-Lyne, with two lines from St. Werburgh's Road to Manchester Airport and East Didsbury. The Phase 3b line from Pomona to the retail concentration at the Trafford Centre would also serve the Imperial War Museum North and Manchester United Old Trafford.

Indicative of effects on passenger numbers caused by extensions, GMPTE identifies a longer-term need for the 'Second City Crossing', whereby congestion on the on-street section including St Peter's Square and Piccadilly Gardens would be reduced by a new direct line from GMex to Victoria.

"With the Phase 3a expansion complete, GMPTE expects over 90,000 journeys will be made daily on Metrolink."

Possible extensions are the completion of a loop from Roundthorn to Manchester Airport via Newall Green and an extension from East Didsbury to Stockport town centre.

GMPTE appointed the M-Pact Thales consortium (Laing O' Rourke, Grant Rail and Thales UK) to design, build and maintain the Phase 3a lines. Construction work started in 2009, with the first operations expected from spring 2011.

With the Phase 3a expansion complete, GMPTE expects over 90,000 journeys will be made daily on Metrolink.

The implementation of a peak-time congestion charge scheme in Manchester was approved by the government in June 2008. The residents of Greater Manchester were called for their opinion regarding the introduction of congestion charge in the region, but about 79% of the people opposed it.

The failed plan, to include peak-time road charge, would have opened up a £2.8bn transport investment. The extension of the line to East Didsbury, Manchester Airport, Ashton-under-Lyne, and the town centres of Oldham and Rochdale was initially linked with the failed plan.

One of the six second-phase trams built for the Eccles extension, at Piccadilly Gardens in Mancheste Anticipated demand from the mediacity development has prompted orders for more trams for the new extension.
The same vehicle, showing how the route at this point mixes very closely with heavily-used bus and p Due to open in 2010, the mediacity branch will leave the Eccles line just west of Harbour City,
A Metrolink tram near Manchester Piccadilly rail terminus. A Metrolink tram near Manchester Piccadilly rail terminus.
Second-tranche tram No 2003 at Broadway, the temporary terminus on the line to Eccles opened in Dece Second-tranche tram at Broadway, the temporary terminus on the line to Eccles.
A notice displayed at Broadway, advising users of the latest progress on the extension to Eccles. A notice displayed at Broadway, advising users of the latest progress on the extension to Eccles.
The £36.5m bus and tram interchange at Central Park was completed in advance of the Manchester-Oldham-Rochdale link.
Light rail has helped redevelopment of the former Manchester Ship Canal docks: Salford Quays.
The Droylsden line will extend from the present Metrolink terminus beneath Piccadilly station.
Tram and bus routes converge in central Manchester at Piccadilly Gardens - high platforms are a feature of Metrolink.
After a long shared road section, Metrolink reaches Eccles through a reserved underpass.