News, views and contacts from the global Railway industry
 

Gotthard Base Tunnel, Switzerland




Key Data


A cultural and trading barrier across Europe for centuries, the Alps remain so for transport. Implications have been marked in Switzerland as traffic has largely been in transit, rather than for Swiss producers or consumers. A motorway construction programme and the opening of the Gotthard road tunnel in 1980 greatly encouraged freight by road. General concern was joined by the shock of the multiple fatalities in the Gotthard and Mont Blanc road tunnel accidents.

To control adverse environmental effects, the Swiss constitution incorporated Protection of the Alps in 1994. Previously during 1992, Die Neuen Eisenbahn-Alpentransversalen (NEAT) or the New Rail Link through the Alps (NRLA) programme was approved for building two base tunnels. These were to be relatively level alignments at lower levels than previous tunnels through the massif on the BLS Lötschberg and SBB Gotthard routes.

Commercial operations through the partially fitted out 34.6km (21.5 mile) Lötschberg base tunnel began in December 2007.

The project

Controls on road freight were only deemed acceptable by surrounding EU countries if better rail infrastructure was created, notably at the Lötschberg and Gotthard pinch points. Even with access to dedicated Rollende Landstrasse (RoLa) trains for transit of complete heavy goods vehicles, both north-south routes had long, slow climbs at either side of tunnels at the respective summits and capacity was limited. The NEAT projects were aimed at removing the main limiting factors for the introduction of more, faster and longer trains on the key Rotterdam-Milan rail corridor.

"The base tunnel will consist of two bores with two track crossovers and multiple interconnections for foot access between the bores."

A 100% Swiss Federal Railways (SBB) subsidiary, AlpTransit Gotthard, was established in May 1998 to deliver the project for the 57km (35.4 mile) Gotthard Base Tunnel. Construction is split into five sections, each with a designated consortium, from the north being: Erstfeld (ARGE AGN), Amsteg (ARGE AGN), Sedrun (ARGE Transco-Sedrun), Faido (ARGE TAT) and Bodio (ARGE TAT).

Other contractors are responsible for many other aspects of the project. The estimated final cost of the project was CHF9.4bn (US$9.0bn) for the Gotthard and 2.24bn for the related 15.4km (9.6 mile) Ceneri tunnel project further south on the route. These amounts exceed the original estimates, with the Swiss parliament approving reserves for uncertainties that included geological conditions, engineering issues and technological developments, the latter relevant due to the long project timescale.

By March 2010, about 94.7% of the planned 151.84km of tunnels, related galleries and passages were excavated.

By September 2010, 23.8% (9.45km) of the 39.78km Ceneri Base Tunnel had been excavated.

By October 2010, about 98.2% (149.1km) of the planned 151.84km of tunnels, related galleries and passages of the Gotthard Base Tunnel had been excavated.

Gotthard Base Tunnel infrastructure

Of slightly different length, the base tunnel will consist of two bores with two track crossovers and multiple interconnections for foot access between the bores. Entirely to the east of the current Gotthard line, access tracks to the new tunnel joining the present line at Erstfeld in the north and Bodio in the south. At a maximum altitude of 550m, the base tunnel is about 600m lower than the present line's summit and overall renders the Gotthard route no more challenging than many other parts of the SBB network.

"By avoiding the climbs, curves and spirals of the original Gotthard, the project will shorten the route by around 40km."

To speed the project, intermediate shafts were sunk to allow for simultaneous tunnelling on several faces, these points (Erstfeld, Amsteg, Sedrun, Bodio and Faido) to become integrated in the finished structure for servicing and emergency access.

Strict environmental control is in place for the work sites, the material supply chain and for the disposal of spoil.

The tunnels are mainly created by tunnel boring machines, with some use of drilling and blasting. The final section, 7.7km from Erstfeld, began in August 2007 and the breakthrough of the tube at Amsteg was carried out in June 2009.

The final breakthrough in the east tube of the Gotthard Base Tunnel took place in October 2010. It took nearly 14 years and 2,500 workers to connect the two ends of the tunnel. This final breakthrough in the west tube was completed in March 2011.

Aside from the much higher speeds that the new alignment will provide, by avoiding the climbs, curves and spirals of the original Gotthard, the project will shorten the route by around 40km (25 miles).

As in the case of the Lötschberg, the old line will be retained for local passenger services, for general capacity and as a diversionary route: a noted part of railway tourism, it also provides an interchange with the east-west metre-gauge network via Göschenen.

Rolling stock

"Planning allows for advances in freight vehicles to allow for speeds up to 160km/h (100mph) through the tunnel."

With freight most constrained by the present line and many trains needing double-heading for both the north and south ramps, an implication is a reduced need for motive power per train. Increased train lengths and weights will be possible through the near-level base tunnel, although in absolute terms the rising traffic demand will not diminish the need for freight locomotives.

Planning allows for advances in freight vehicles to allow for speeds up to 160km/h (100mph) through the tunnel. Longer trains and more of them allow for doubling the present freight capacity on the Gotthard route, much of which will be intermodal services, with Alp Transit setting the amount at around 40 million tonnes annually.

Domestic passenger services south to Chiasso and Locarno are likely to be formed in part by a next generation of Swiss coaching stock or units cascaded from elsewhere on the SBB network. Entering line testing in 2008, the ETR 610 from Alstom Ferroviaria is to become the flagship high-speed unit operating Cisalpino services between Switzerland and Italy. For Zurich-Milan, a 50min reduction to 2h50min by Cisalpino units is envisaged.

Signalling and communications

Following settlement of a legal challenge over the initial selection, the last major contract signed (CHF1.69bn in April 2008) for the Gotthard project was with the Transtec Gotthard Consortium to fit out the tunnel and approach tracks. Starting at the south portal, the work began in September 2009.

As installed in the Lötschberg, the Gotthard and Ceneri tunnels are to be fitted with ETCS / ERTMS Level 2 that obviates trackside signals. A leading adopter of the EC-sponsored system, non-EC Switzerland is advanced in the equipping of its rolling stock with the required equipment.

Thales, as part of the Transtec Gotthard Consortium, will supply, install and test all the ETCS Level 2 systems and the Centralised Traffic Control Systems.

Contractors

In April 2011, a consortium of ABB and TLT Turbo GmbH won a $45m contract to provide a ventilation system for the Gotthard Base Tunnel. The contract involves supplying medium-voltage and low-voltage switchgear and other electrical equipment, and carrying out cable design and delivery, installation, assembly and commissioning of other components.

The future

Two aspects of the original project have been postponed indefinitely. The Porta Alpina deep level station planned as part of the Sedrun access point was shelved in September 2007 over concerns relating to cost, value and technical issues.

The 11km second phase of the Zimmerberg base tunnel on the Zurich-Zug section has also been dropped. Becoming the world's longest railway tunnel, commercial operation of the Gotthard Base Tunnel with scheduled train services is now planned to start no earlier than the end of 2017.

Gotthard Base Tunnel By avoiding the curves and spirals of the classic route, the Gotthard Base Tunnel will shorten journeys by 40km (South Ramp, Ticino).
Freight Railway Network A mixed railway, capacity limits on the present Gotthard route mean that freight trains await paths at several points.
Swiss Rail Network Opened in 1882, the current 15km Gotthard tunnel will be retained as part of the Swiss network.
Old and new Gotthard rail routes.
The twin south portal at Bodio close to where the old and new routes will join.
Zimmerberg Base Tunnel Of the three projects on the Zurich-Milan axis, the Zimmerberg base tunnel has been postponed indefinitely.
Gotthard Tunnel Access Points Access points to increase tunnelling progress and for emergency access was created at Sedrun. The projected Porta Alpina station has been shelved.
Gotthard Base Tunnel Construction Breakthrough by a tunnel boring machine of the Gotthard Base Tunnel.