The US Massachusetts Bay Transportation Authority (MBTA) has unveiled plans to fast-track its infrastructure projects for subway lines and Commuter Rail.

MBTA aims to deliver improved service, safety and reliability.

It has scheduled to deliver the projects eight years ahead of the original plan. This will include track replacement, upgraded intersections and station improvements.

The project will lead to more diverted weekend services on several lines.

In addition to major weekday outages, the plan calls for two one-month shutdowns on the Green Line. Single month shutdowns will also take place on C Branch in July and E Branch in August.

Governor Charlie Baker said: “Our administration is dedicated to building a better MBTA for our riders that is safer and more reliable and the 2020 Infrastructure Acceleration Plan will help to achieve this goal faster.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

“The MBTA started these projects in 2019 and will continue a vigorous schedule of construction and repairs aimed to build a system that will move more people from point to point in less time. The T has worked hard to minimise disruptions for riders for the 2020 projects by continuing to provide alternative transportation services and has also developed a new web map so riders can get the information easily during this process.”

From May, MBTA will suspend the regular Green Line service from North Station to Lechmere for 11 months.

MBTA will accelerate efforts to improve the Lechmere Viaduct. It will fast track the reconstruction of the elevated segment of the track via East Cambridge.

Additionally, it will carry out the realignment of the track to a new Lechmere Station.

To mitigate disruptions to passengers during the diversions, the MBTA plans to increase the frequency of parallel services. It will also offer accessible shuttle buses.

MBTA said that it will not charge customers for the shuttle buses.

It will enforce speed restrictions at locations undergoing track work out as a precautionary measure.

The restrictions will be removed after the proper settlement of the tracks has been confirmed.