The consortium comprising ZUE, Budimex and STRABAG has concluded modernisation of the Żychlin-Barłogi stretch (LCS Kutno) on the E-20 railway line in Poland.

The project has been completed eight days ahead of schedule.

Modernisation works, which started in April 2017, required a complete line closure. Traffic was redirected on a detour and special buses.

Budimex carried out works at the Zamków rail yard, Barłogi station and the Barłogi route at the LCS Kutno border.

Budimex said it continued construction 24 hours a day to reduce the duration of these alternate routes. An 18km-long surface was built along the LCS Kutno by disassembling the existing track and ground reinforcement.

ZUE communications director Grzegorz Krzystański said: “Cooperation between companies from the consortium ran smoothly. We were all keen to finish our activities as soon as possible and reopen the route. Thanks to proper organisation and around-the-clock work, we put the track into operation on 9 June, one week before the contractual deadline.”

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Headquartered in Poland, Budimex is one of the leading railway contractors in the country. It also involved in the reconstruction of Olszamowice station and modernisation of the railway line in Warsaw.

The project, which will be completed by 2020, is set to cut travel time between Poznań and Warsaw by two hours and 20 minutes.

Additionally, Budimex is working on railway line number 7 (Otwock-Dęblin) modernisation, reconstructing the E59 railway line (Rokietnica-Wronki), and construction on LCS Idzikowice. All of these will be completed by 2020.