News, views and contacts from the global Railway industry
 

Lima Metro, Peru




Key Data


Lima

Lima Metro, also called Tren Eléctrico, is a rapid transit metropolitan railway that serves Lima, the capital city of Peru. It provides a transport link between different suburbs of the city with a population of over eight million.

Line 1 of the Lima Metro was put into operation in January 2012. Proposals for construction of Line 2 of the metro were accepted in 2012. A consortium led by Geodata Engineering was awarded the consultancy contract in July 2012. Three consortiums were shortlisted for the concession contract of the Line 2 in February 2014.

The 30-year concession contract was finally awarded to a consortium led by ACS and FCC in March 2014. The consortium will design, finance and build the line 2 in five years, and will operate and maintain the line for 30 years. The contract is valued at €3.9bn ($5.36bn).

History of the Lima Metro project

"In December 2009, Tren Electrico Lima consortium, comprising Grana y Montero and Norberto Odebrecht, was selected as the winning bidder for the construction of the line, for $410.2m."

The proposals for a mass rapid transit system to serve the city of Lima were made in 1970s, with construction starting in 1986 but was abandoned midway as the country's economy plunged into a deep economical and social crisis.

The project resumed in 2008 and tenders were issued by the government's private investment agency ProInversion. Several consortia were interested in the bid, which included construction and operation of Line 1 for a concession period of 40 years, including Acciona and Graña y Montero, Metro de Madrid and OHL and Cobra and Abengo-Telent. A length of 9.2km of the line was already constructed, with the winner constructing the remaining 12.3km stretch and operating the whole line. The tender was, however, abandoned due to lack of funding for the project.

In December 2009, Tren Electrico Lima consortium, comprising Grana y Montero and Norberto Odebrecht, was selected as the winning bidder for the construction of the line, for $410.2m. Work on the line started in March 2010 and included the construction of nine new stations and installation of new electromechanical equipment for the entire route. The total cost of the project was estimated to be around $549m, with Corporación Andina de Fomento granting a loan of $300m.

In March 2011, ProInversion awarded Tren Lima (consortium of Graña y Montero and Ferrovías) the operation and maintenance contract of the metro for a concession period of 30 years. An investment of $290m was put forth for the project by the consortium, with around $200m from the investment set to be used for the purchase of new rolling stock.

Corporación Andina de Fomento agreed to fund a feasibility study of phase II of Line 1 of the metro in 2010. The second phase includes a 27km north extension of Line 1.


Related project


São Paulo Metro, Brazil

The São Paulo metro system consists of five colour-coded lines – Line 1-Blue, Line 2-Green, Line 3-Red, Line 4-Yellow and Line 5-Lilac. Lines 1, 2, 3 and 5 are operated by the state-owned Companhia do Metropolitano de São Paulo (São Paulo Metro) and Line 4 by a consortium led by ViaQuatro, a local operator.


Tren Eléctrico routes

Line 1 of the Lima Metro is 22km long, including a total of 16 stations, starting from Villa El Salvador to Miguel Grau. The whole stretch runs on standard (1,435mm) gauge and 1500V DC power supply, and is being extended northwards to stretch to over 33.98km with an additional ten stations.

The Lima Metro rolling stock

Line 1 is currently served by 42 train sets designed by Ansaldo Breda, while Alstom was awarded a $158.6m contract to supply 19 five-car Metropolis train sets for operation on Line 1. These trains have low floor, wide doors, extra-wide seats and extra width to ensure free flow of passengers. They also allow maximum natural light to enter inside the vehicle and are fitted with information displays. The first train set of the order was delivered in late 2012 and became operational in 2013.

Tren Eléctrico signalling and communication

Bombardier was awarded a $19.36m contract for the supply of Cityflo 350 signalling for Line 1. The contract included the installation of interlocking, track circuits and control equipment on the entire line.

The Cityflo 350 signalling system includes onboard automatic train protection (ATP) and automatic train operation (ATO). Both the systems are integrated with a display in the driver's cabin.

Lima Metro line 2 details

The Line 2 of the metro will stretch 27km and will be underground with 27 stations. It will connect Ate in Lima with the Callao region, bordering the capital and intersecting Line 1 at Miguel Grau.

"Lima Metro, also called Tren Eléctrico, is a rapid transit metropolitan railway that serves Lima, the capital city of Peru."

Charities Aid Foundation Bank has agreed to issue a loan of $600m for 18 years and a grace period equivalent to construction phase of the line. Line 3 and Line 4 of the metro are also being proposed. An 8km branch from line 4 connecting to the International Airport will also be built with eight underground stations.

Lima Metro is a rapid transit metropolitan railway service serving Lima, the capital city of Peru.
Regular services on the first line of Lima Metro were started in January 2012.
Line 1 of Lima Metro operates rolling stock supplied by Ansaldo Breda.
Lima Metro provides a comfortable transport link to different suburbs of the city.